S.# | Project Title | Year | Project Duration | Project Location | Project Cost (PKR) | Donor/Partner | Thematic Area | Logo | |
1 | Construction of 4 Km Jeep road | 2000 | 06 Months | U/C Jabori)
District Mansehra |
2,147,670 | German Technical Cooperation | Sustainable Livelihoods | ||
2 | Construction of 3000 meter Drinking Water Supply Scheme | 2001 | 06 Months | Thakra (U/C Karori) District Mansehra | 200,000 | German Embassy | WASH | ||
3 | Strengthening and up-gradation of Joint Forest Management Plan through Biodiversity Conservation | 2002 | 12 Months | UC Fateh Bandi District Mansehra | 125,000 | WWF-Scientific Committee | Climate Change | ||
4 | Upper Siran Biodiversity Conservation Project | Apr, 2003- Dec 2006 | 24 Months | Methal, Hafizabad, Bandhodar (UC Jabbori) District Mansehra | 2,728,125 | UNOPs/UNDP (GEF) | Climate Change | ||
5 | Improving Families Livelihoods through Backyard Poultry Farming | Oct, 2004-Dec, 2006 | 12 Months | 9 Selected UCs of District Mansehra | 3,738,821 | Plan International | Sustainable Livelihoods | ||
6 | Development of Families Livelihoods through Livestock Development for selected Plan Communities in District Manshera | Dec 2006-Dec 2008 | 24 Months | 4,337,630 | Plan International | Sustainable Livelihoods | |||
6 | Upper Siran Human and Natural Resource Development Project | Jun, 2004-Jun, 2007 | 37 Months | Methal, Nikki Mohri, Bandhodar and Dagra villages of UC Jabori District Mansehra | 9,572,286 | Austrian Development Agency
Eco-Himal |
Climate Change | ||
7 | Families Re-unification and Child protection Program in the Camps of Earthquake Affectees of District Mansehra | 2005-06 | 12 Months | Kashtara and Jabba Camps District Mansehra | 6,085,884 | UNICEF | Emergency | ||
Mobilization, Coordination and Installation of Shelters for Pakistan Earthquake Victims in Siran Valley Mansehra | Mar-Apr 2006 | 03 Months | Siran Valley
District Mansehra |
700,000 | German Technical Cooperation | Emergency | |||
Support to Spontaneous Shelter Recovery in Earthquake Affected Villages in Pakistan | Nov-Dec 2005 | 45 Days | Siran Valley
District Mansehra |
1,439,150 | UN-HABITAT | Emergency | |||
8 | Promotion of Himalayan Temperate Forests in Sharkool Valley of District Mansehra | September 2005 – June, 2007 | 22 Months | UC Chatter Plain District Mansehra | 5,704,978 | UNDP-PTF | Climate Change | ||
9 | ADA-Rehabilitation Project | March 1, 2006 –May 30,2008 | 27 Months | Methal, Nikki Mohri, Bandhodat and Dagra villages of UC Jabori District Mansehra | 16,491,704 | Austrian Development Agency
Eco-Himal |
Emergency | ||
10 | Paul 3×3 (Education Program) | March 2006 –June 30 2011 | 64 Months | 3 UCs of Upper siran valley District Mansehra | 7,913,104 | HAASHAR Netherland | Education | ||
11 | Supporting Early Recovery of Livelihoods in Siran Valley, Pakistan | Mar 2006 – Sept 2006 | 07 Months | UC Jabbar Devli District Mansehra | 31,361,495 | Concern Worldwide | Sustainable Livelihoods | ||
12 | Livelihoods Rehabilitation Project in Siran Valley | Oct 01, 2006-Dec 2006 | 03 Months | UC Jabbar Devli District Mansehra | 10,214,740 | Concern Worldwide | Sustainable Livelihoods | ||
13 | Siran Valley Livelihoods Rehab Program | Jan 1, 2007-Dec 31, 2008 | 24 Months | Bhogarmang, Sachan, Devli and Jabori U/Cs District Mansehra | 131,001,928 | Concern Worldwide | Sustainable Livelihoods | ||
14 | Child and Adolescent Protection Project | January 2007- December, 2008 | 24 Months | UC Hilkot & Bhogarmang District Mansehra | 8,664,793 | UNICEF | |||
15 | Earthquake Rehabilitation & Reconstruction Project | June 1,2007-Dec 31,2008 | 19 Months | Bhogarmang, Sachan, Devli and Jabori U/Cs District Mansehra | 120,664,941 | Concern Worldwide | Sustainable Livelihoods | ||
16 | Community Based Livelihoods Development Programme (CBLDP) | January-December 2009 | 12 Months | Bhogarmang, Sachhan, Devli and Jabori U/Cs District Mansehra | 18,650,597 | Concern Worldwide | Sustainable Livelihoods | ||
17 | Emergency Humanitarian Assistance in 3 Flood affected UCs of District Shangla | Sept 30- December 29, 2010 | 04 months | Kuz kana, Dhamori, Opal and Shahpur UCs District Mansehra | 20,779,220 | Concern Worldwide | Sustainable Livelihoods | ||
18 | Mansehra Food Security Project (MFSP) | January 1, 2010 -November 2011 | 10 Months | Bhogarmang, Sachhan, Devli and Jabori U/Cs District Mansehra | 41,508,419 | Concern Worldwide | Sustainable Livelihoods | ||
19 | Improving families Livelihoods through backyard poultry Farming | 2005 | 12 Months | 9 Selected UCs of District Mansehra | 1,730,243 | Plan International | Sustainable Livelihoods | ||
20 | Development of Families Livelihood through Livestock development for selected Plan communities in Mansehra | March 1, 2006 –May 30,2008 | 24 Months | 9 Selected UCs of District Mansehra | 2,751,100 | Sustainable Livelihoods | |||
21 | Supporting Early Recovery of Livelihoods in Konsh Valley, Pakistan | May 15, 2006-Sept 15, 2006 | 04 Months | Selected Villages of Chattar and Hilkot UCs
District Mansehra |
4,062,750 | CHF/CIDA | Sustainable Livelihoods | ||
22 | Post Earthquake Sustainable Livelihoods Rehabilitation in Konsh Valley-NWFP (now KPK) | Jan 30, 2007-Dec 31, 2008 | 24 Months | Ichhrian, Battal, Hilkot and Chattar Plain U/Cs
District Mansehra |
106,490,114 | CHF/CIDA | Sustainable Livelihoods | ||
23 | Sustainable Women Economic Empowerment In Shangla (SWEETISH) Project | Dec 1, 2010-Jan 31, 2011 | 02 Months | Damori U/C
District Shangla |
320,000 | Misereor Germany | Sustainable Livelihoods | ||
24 | Equipment of Winterized Shelters in the Upper Siran Valley with Fuel efficient Stoves, Bathrooms, Hygiene Kits, Mattresses | Jan-April 2006 | 04 Months | Methal, Hafizabad, bandhodar (UC Jabbori) District Mansehra | 11,134,761 | Misereor
Germany |
Emergency | ||
25 | Further support of the people of Bandhodar in upper Siran valley in NWFP in order to enable them to earn their livelihoods | May 2006-2008 | 24 Months | Methal, Hafizabad, bandhodar (UC Jabbori) District Mansehra | 16,132,054 | Misereor
Germany |
Emergency | ||
26 | Restoration and Improvement of Sustainable Livelihoods in the Siran Valley of NWFP-Pakistan | 2006-2008 | 24 Months | Methal, Hafizabad, bandhodar (UC Jabbori) District Mansehra | 286,946,72.9 | Misereor
Germany |
Sustainable Livelihoods | ||
27 | Emergency Humanitarian Assistance in 3 flood affected Union Councils of District Shangla | April 13- September 14, 2011 | 05 Months | Kuz kana, Opal and Shahpur UCs DSistrict Shangla | 19,925,597 | Concern Worldwide (RAPID) | Emergency | ||
28 | Restoration of Flood Affected Rural Economic Structures Humanitarianly (REFRESH) | May 2011, Oct 2011 | 06 Months | U/C Ghanool, Kaghan Valley District Mansehra | 5,245,000 | Misereor Germany | WASH | ||
29 | PEER Integrated Education Program | Aug 2010-Dec 2013 | 40 Months | Jabbar Devli, Sum and Bhogarmang U/C District Mansehra | 20,719,320 | Catholic Relief Services | Education | ||
30 | Restoration and Improvement of Sustainable Livelihoods in Konsh Valley (RISLK) | January 2009-November 2012 | 35 Months | Ichhrian, Battal, Hilkot and Chattar Plain UCs of Konsh Valley District Mansehra | 155,983,334 | CHF/CIDA | Sustainable Livelihoods | ||
31 | Educate A Child Proect under
Pakistan Education Support Program (PESP) |
July 2014-todate | Continuous | Districts Abbottabad, Mardan and Peshawar | Open | Canadian Association for Children Education in Pakistan (CACEP) | Education | ||
32 | Micro Hydel Power Projects Abbottabad/Batgram
(Consortium of four organizations lead by Haashar) |
Sept 2014 todate | 18 Months (extendable) | Districts Abbottabad and Batgram | 730,000,000 | Government of KP through Pakhtunkhwa Energy Development Organization | Renewable Energy | ||
33 | Micro Hydel Power Projects Mansehra
(Consortium of four organizations lead by Haashar) |
May 2017 to-date | 12 Months (Extendable) | District Mansehra | 700,000,000 | Government of KP through Pakhtunkhwa Energy Development Organization | Renewable Energy | ||
34 | Livelihood Improvement through Livestock Development in Hazara Division of KP Province (Base Line Survey current practices) | May –July 2021 | 3 Months | District Abbottabad,
Mansehra, Haripur |
3,536,900 | Japan International Cooperation Agency | Sustainable Livelihoods | ||
35 | Livelihood Improvement through Livestock Development in Hazara Division of KP Province (Base Line Survey Milk Marketing) | Jan-Mar 2022 | 3 months | District Abbottabad,
Mansehra, Haripur |
1,536,095 | Japan International Cooperation Agency | Sustainable Livelihoods | ||
36 | Environmental Rehabilitation Project Manoor Valley (ERP-M) | May-Oct 2023 | 6 Months | Manoor Valley District Mansehra | 6,831,934 | Australian High Commission Islamabad | Climate Change | ||
37 | Kohistan Early Recovery Project (KERP I) | April-June 2023 | 3 Months | Dubair Valley of District Kohistan | 3,516,000 | German Rotary | Emergency | ||
38 | Manoor Education Support Project
Distribution of School Bags and Stationery among School Girls in Manoor Valley |
July August 2023 | 3 Months | District Mansehra (Manoor Valley) | 500,000 | German Embassy | Education/Emergency | ||
39 | Kohistan Early Recovery Project (KERP II) | Oct-Dec 2023 | 3 Months | District Kohistan | 3,276,000 | German Rotary | Emergency | ||
40 | Environmental Protection and Awareness in Manoor Valley Project | Feb-July 2024 | 6 Months | Manoor Valley of Mansehra | 7300043 | Australian High Commission Islamabad | Climate Change |